Question

To ask the Scottish Government how many electric vehicle charging points have been installed at Scottish Government buildings or premises in each of the last four financial years, including 2021-22 to date, also broken down by the building concerned.


Answer

The following electric vehicle charging points have been installed at Core Scottish Government buildings or premises in each of the last four financial years, including 2021-22 to date

2018-2019

Dumfries

2 x wall mounted smart sockets

Thurso

2 x wall mounted smart sockets

Bonnington, Edinburgh

8 x wall mounted smart sockets

Saughton House, Edinburgh

1 x 22kW dual charging post

Victoria Quay, Edinburgh

1 x 22kW dual charging post

2019-2020

Victoria Quay, Edinburgh

6 x 7kW dual outlet

1 x 50kW triple outlet

1 x 22kW dual outlet

Saughton House, Edinburgh

1 x 22kW dual outlet

4 x 7kW dual outlet

Marine Lab, Aberdeen

4 x 7kW dual outlet

2 x 22kW dual outlet

Faskally

1 x 7kW dual outlet

Cameron House, Oban

2 x 7kW dual outlet

1 x 22W dual outlet

Longman House, Inverness

2 x 22W dual outlet

Atlantic Quay, Galsgow

1 x 7kW dual outlet wallbox

Tankerness, Orkney

1 x 7kW dual outlet wallbox

Stornoway

1 x 7kW dual outlet wallbox

2020-21

Projects delayed due to Covid.

2021-2022

Victoria Quay, Edinburgh

1 x 22kw dual outlet

Saughton House, Edinburgh

2 x 22kw dual outlet