Question reference: S4W-17248
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
- Date lodged: 17 September 2013
-
Current status: Answered by Nicola Sturgeon on 1 October 2013
Question
To ask the Scottish Government how much it would cost to include the Dalmeny chord in the Edinburgh Glasgow Improvement Programme using a (a) flat and (b) grade-separated junction.
Answer
The original estimate for the full Edinburgh Glasgow Improvement Programme included provision of £175 million for the Dalmeny Chord. The estimate included two grade separated junctions and one flat junction.