Question reference: S5W-32871
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
- Date lodged: 28 October 2020
-
Current status: Answered by Roseanna Cunningham on 11 November 2020
Question
To ask the Scottish Government, further to the answer to question S5W-10494 by Roseanna Cunningham on 15 August 2017, which of the 42 formal flood protection schemes or engineering works have been completed, broken down by (a) the number of properties being protected, (b) the completion date and (c) what the (i) initial forecast and (ii) final cost was of each.
Answer
Details are as follows:
Scheme | (a) Properties Protected | (b) Completion Date | (c)(i) Initial Cost (£ million) (1) | (c) (ii) Estimated Final Cost (£ million) |
Huntly | 63 | 2017 | 4.9 | 3.8 |
Newmill | 18 | 2017 | 1.9 | 1.8 |
Dundee | 200 | 2018 | 6.2 | 6.9 |
Kirkwall | 750 | 2018 | 1.8 | 1.8 |
White Cart Water Phase 3 | 100 | 2019 | 5.9 | 7.2 |
Camlachie Burn | 410 | 2019 | 1.2 | 1.7 |
Broxburn (Liggat Syke) | Not held | 2019 | Not held | Not held |
New Cumnock Phase 1 Complete Phase 2 Under construction | 95 | P1 2018 P2 July 2022 | 3.3 | 6.2 |
(1) Note: Initial costs as provided by local authorities in 2016-17.