Question reference: S6W-04810
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
- Date lodged: 3 December 2021 Registered interest
-
Current status: Answered by Shona Robison on 17 December 2021
Question
To ask the Scottish Government what the (a) target and (b) actual average timescale has been for assessing applications for grant assistance to deliver affordable housing above Affordable Housing Investment Benchmark level, in each quarter since Q1 2016.
Answer
The Scottish Government does not set a target timescale for assessing applications for grant assistance to deliver affordable housing above the applicable affordable housing investment benchmark level.
Using information from our Housing and Regeneration Programme system (HARP), we have compiled the following table showing the average calendar days from the initial tender application submission date to the actual tender approval date for those projects submitted at above benchmark level over the period Quarter 3 2017-18 to Quarter 2 2021-22. It should be noted, however, that while we encourage early engagement on likely project costs prior to tender applications being submitted, there can be instances where applications have missing information or require further, more detailed work by the grant applicant before they can be fully assessed.
Financial year quarter | Total projects approved above the applicable benchmark | Average time between the initial tender submission and the actual approval date |
(calendar days) | ||
2016-17 Q1 | 5 | Data not available |
2016-17 Q2 | 7 | Data not available |
2016-17 Q3 | 20 | Data not available |
2016-17 Q4 | 45 | Data not available |
2016-17 Total/ Average | 77 | Data not available |
2017-18 Q1 | 16 | Data not available |
2017-18 Q2 | 14 | Data not available |
2017-18 Q3 | 14 | 22 |
2017-18 Q4 | 41 | 19 |
2017-18 Total/ Average | 85 | 20 |
2018-19 Q1 | 10 | 41 |
2018-19 Q2 | 13 | 30 |
2018-19 Q3 | 22 | 33 |
2018-19 Q4 | 47 | 26 |
2018-19 Total/ Average | 92 | 30 |
2019-20 Q1 | 19 | 31 |
2019-20 Q2 | 14 | 38 |
2019-20 Q3 | 35 | 25 |
2019-20 Q4 | 82 | 25 |
2019-20 Total/ Average | 150 | 27 |
2020-21 Q1 | 9 | 19 |
2020-21 Q2 | 16 | 44 |
2020-21 Q3 | 17 | 27 |
2020-21 Q4 | 30 | 29 |
2020-21 Total/ Average | 72 | 31 |
2021-22 Q1 | 12 | 21 |
2021-22 Q2 | 21 | 42 |
2021-22 Total/ Average | 33 | 35 |
Data on tender submission dates from Quarter 1, 2016-17 to Quarter 2, 2017-18 is not available as this pre-dated our HARP system and the historic information was not migrated to HARP.