Question

To ask the Scottish Government whether it will confirm the initial budget for Scottish rail infrastructure renewals and enhancements for Control Period 6.


Answer

The published Statement of Funds Available (SOFA) covers funding available towards Network Rail operations, maintenance and renewal activities in Scotland as well as enhancement projects. The funding available for Control Period 6 as per the SOFA includes allocation for the completion of projects which carry over from Control Period 5 as well as projects commencing in Control Period 6.

As per the Statement of Funds Available, the budget figure for Control Period 6 in Scotland is £4.85 billion. We are currently in the process of considering the basis on which the funding required for Control Period 7 will be determined and expect this to be reflected in a further SOFA publication to align with the commencement of Control Period 7 anticipated as April 2024.

Further information on the SOFA can be accessed via:- sofa-2019-24-25-jan-2018.pdf (transport.gov.scot)