Question

To ask the Scottish Government whether it will provide an update on what the estimated cost has been of establishing Social Security Scotland, and what the estimated (a) staff and running cost and (b) budget for the provision of social security payments is for (i) the current financial year and (ii) each of the next four years.


Answer

The Programme Business Case, published in February 2020, provides future forecasted operating costs for Social Security Scotland. The link to the Business Case can be found at the following link: https://www.gov.scot/publications/social-security-programme-business-case-executive-summary/documents/

The 2021-22 Autumn Budget Revision, published on 27 September 2021, set out the financial position for Social Security in the current year. The Social Security budget line captures staff and running costs, and Social Security Assistance covers benefits expenditure. The document can be found at the following link: https://www.gov.scot/publications/2021-22-autumn-budget-revision-budget-scotland-act/

The 2022-23 Scottish Budget, which is set to be announced on 9 December 2021, will set out what the Scottish Government will invest in Social Security over the next financial year. The 2021 Medium Term Financial Strategy will be published alongside the new Budget and will focus on the fiscal position within the Parliamentary term.