Skip to main content

Language: English / GĂ idhlig

Loading…

Chamber and committees

Question reference: S6W-01885

  • Asked by: Ross Greer, MSP for West Scotland, Scottish Green Party
  • Date lodged: 27 July 2021
  • Current status: Answered by Graeme Dey on 20 August 2021

Question

To ask the Scottish Government, further to the answer to question S6W-00982 by Graeme Dey on 8 July 2021, how much of the £5 million budget referred to was spent on the platform extension project at Milngavie railway station; what the total cost was of the platform extension project, and where additional funds were sourced from.


Answer

Of the £5M budget available in FY 20-21, £4.8M was spent on the Milngavie platform works. The total cost of the works was £5.55M. The additional funding was provided by Scottish Ministers through funding allocated to Network Rail in Control Period 6.