Question

To ask the Scottish Government how many affordable homes that are due for completion in 2021-22 are subject to (a) delays and (b) cost increases because of the shortages of materials and price increases that were recently reported by the Federation of Master Builders.


Answer

There are a large number of affordable housing supply programme projects on site at the moment across the country and we are aware that some are subject to delays. My officials are therefore gathering local intelligence through the More Homes Division Area Team network, as well as maintaining links with the trade body Homes for Scotland, to monitor this. The Scottish Government is aware of concerns around price increases and supply shortages of construction materials. We are working closely with the construction industry through the Construction Leadership Forum, chaired by Ivan McKee MSP, Minister for Business, Trade, Tourism and Enterprise, to fully understand the current supply chain issues and, where possible, to put in place mitigating actions to address the issues that are being identified.

I will continue to be advised of developments in regard to materials cost increases and availability, as well as any impact being seen on the Affordable Housing Supply Programme going forward.