Question reference: S6W-00623

  • Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
  • Date lodged: 11 June 2021
  • Current status: Answered by Humza Yousaf on 25 June 2021

Question

To ask the Scottish Government whether it will provide a breakdown of the additional costs associated with the remedial works and delayed opening of the new Royal Hospital for Children and Young People in Edinburgh.


Answer

The cost of rectification for the Royal Hospital for Children and Young People in Edinburgh project is £16.8 million. This consists of: £10.3 million relating to remedial works at the new facilities; £2.8 million for maintaining existing sites; and £3.7 million project and professional costs relating to ongoing project management and required specialist review.