Question reference: S5W-36053

  • Asked by: Bill Bowman, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: 11 March 2021
  • Current status: Answered by Michael Matheson on 23 March 2021

Question

To ask the Scottish Government by what date the Haudagain improvement project (a) was initially expected and (b) is currently expected to be open to traffic.


Answer

The construction of the A92/A96 Haudagain Improvement project is progressing. Due to the Covid-19 pandemic and the measures to combat the impact of the pandemic, as confirmed in the recent publication of the Infrastructure Investment Plan in December 2020 completion has changed from the original published date of Spring 2021 and is now anticipated in Winter 2021.

While this date is subject to any further impacts of the pandemic and unforeseen circumstances such as the effects of exceptional weather, Transport Scotland is working with the contractor to review the programme of work and identify any actions which may help to mitigate delays where possible.