Question reference: S5W-32871

  • Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
  • Date lodged: 28 October 2020
  • Current status: Answered by Roseanna Cunningham on 11 November 2020

Question

To ask the Scottish Government, further to the answer to question S5W-10494 by Roseanna Cunningham on 15 August 2017, which of the 42 formal flood protection schemes or engineering works have been completed, broken down by (a) the number of properties being protected, (b) the completion date and (c) what the (i) initial forecast and (ii) final cost was of each.


Answer

Details are as follows:

Scheme

(a) Properties Protected

(b) Completion Date

(c)(i) Initial Cost

(£ million) (1)

(c) (ii) Estimated Final Cost

(£ million)

Huntly

63

2017

4.9

3.8

Newmill

18

2017

1.9

1.8

Dundee

200

2018

6.2

6.9

Kirkwall

750

2018

1.8

1.8

White Cart Water Phase 3

100

2019

5.9

7.2

Camlachie Burn

410

2019

1.2

1.7

Broxburn (Liggat Syke)

Not held

2019

Not held

Not held

New Cumnock Phase 1 Complete

Phase 2 Under construction

95

P1 2018

P2 July 2022

3.3

6.2

(1) Note: Initial costs as provided by local authorities in 2016-17.