To ask the Scottish Executive what its latest estimates are of the (a) cost and (b) date of completion of the (i) Stirling/Alloa/Kincardine rail line, (ii) Borders rail line, (iii) Airdrie to Bathgate rail line, (iv) Glasgow Airport rail link, (v) M74 completion, (vi) upgrade of the M80 Stepps to Haggs, (vii) M8 Baillieston to Newhouse project and (viii) A90 Aberdeen Western Peripheral Route.
Latest estimates forthe following projects:
(i) Stirling/Alloa/KincardineRail Line
The cost for the construction of the Stirling – Alloa – Kincardine project is currently estimated tobe up to £85 million and the project remains on target to commission in March 2008with operational services forecast to commence in May 2008.
(ii) Borders RailLine
Transport Scotland is continuing a due-diligence review of the Borders railwayas it prepares to take on the role of Authorised Undertaker for the railway, a rolethat it is assuming at the behest of the previous Administration. Therefore, untilthis exercise is complete, it is not prudent to speculate what the final cost anddate of completion of the project is likely to be.
(iii) Airdrie to BathgateRail Line
The estimated costof the Airdrie to Bathgate rail line is an outturn of up to £375 million, with adelivery date of December 2010.
(iv) Glasgow Airport Rail Link
As announced in Parliament on 27 June 2007, StrathclydePartnership for Transport (SPT) and Network Rail (NR) are working together to combinethe Glasgow Airport Rail Link (GARL) with NR’s Paisley Corridor Renewal (PCR) project,with the consequence that GARL services would be introduced around a year laterthan previously advised.
Transport Scotland, SPT and NR have, over the Parliament’ssummer recess, worked to develop the detailed schedule, cost and risk models forthe integrated projects and we will provide the Parliament with an update as soonas is possible.
The integration of these two projects will minimise thedisruption on what is one of Scotland’s busiest rail corridors.
(v) M74 Completion
The current cost estimateis £375 million to £500 million. The project is currently being tendered and thefinal cost and delivery date will not be known until this process is concluded.
(vi) Upgrade of theM80 Stepps to Haggs
The current cost estimateis in the range £130 million - £150 million. The project is currently being tenderedand the final cost will not be known until this process is concluded. We anticipateconstruction completion 2010-11
(vii) M8 Bailliestonto Newhouse Project
The current cost estimateis in the range £170 million - £210 million, based on the risks as currently identified,but we will continue to monitor both in light of prevailing tender prices for roadscontracts. We anticipate construction completion 2012-13.
(viii) A90 AberdeenWestern Peripheral Route
The current cost estimateis in the range £295 million - £395 million, based on the risks as currently identified,but we will continue to monitor both in light of prevailing tender prices for roadscontracts. We anticipate construction completion by the end of 2012.