Current status: Answered by Gillian Martin on 11 August 2026
To ask the Scottish Government what assessment it has made of any potential cumulative impact of hyperscale data centres on water supply in Scotland.
Any proposals for new data centres would be subject to the statutory planning process, which would consider a range of factors including water resources, environmental impacts and wider infrastructure capacity. It is Scottish Ministers' expectation that new developments are designed and located in a way that supports long-term sustainability and water resilience.
Scotland's existing data centres account for a very small proportion of public water demand, and early engagement with developers is important to ensure proposals are aligned with local infrastructure and environmental considerations. There are opportunities for some future developments to make use of treated wastewater, helping to support economic growth while protecting drinking water supplies and the environment.