Skip to main content
Loading…

Chamber and committees

Question reference: S7W-00006

  • Asked by: Emma Roddick, MSP for Inverness and Nairn, Scottish National Party
  • Date lodged: 14 May 2026
  • Current status: Answered by Stephen Flynn on 26 May 2026

Question

To ask the Scottish Government whether it will provide an update on its commitment to dualling the A96, particularly in relation to the completion of the Nairn Bypass, at the earliest practicable opportunity.


Answer

As outlined in our pledge over the first 100 Days of a new government and as set out in the Scottish Budget 2026-27, Scottish Spending Review 2026 and the Infrastructure Delivery Pipeline 2026, published on 13 January, the Scottish Government is fully committed to dualling the whole A96, including a Nairn Bypass. As part of this commitment the Scottish Government is already starting the dualling process from Inverness to Nairn, including Nairn Bypass.

Investment in the trunk road network over the four year Capital Spending Review period to 2029-30 will allow the Scottish Government to make further progress on dualling the A96 between Inverness and Nairn, including the Nairn Bypass. With the land acquired for the scheme in 2025, funding is included in the 2026-27 Budget to commence the delivery of advanced works. This will include vital archaeological investigation works and other key environmental and ecological measures, along with significant work to facilitate complex Public Utility diversions.

In parallel to the advanced works, investment through the Budget in 2026-27 will also allow Transport Scotland to continue to take forward the work to determine the most suitable procurement option for delivering the scheme and further develop the Business Case.

The Scottish Government’s preference would be to deliver the A96 Dualling Inverness to Nairn (including Nairn Bypass) as one project. However, due to the continued fiscal challenges, it is planned that the Scottish Government will take forward a phased approach to delivery, starting with the Nairn Bypass, followed by the remaining sections of the scheme, from Seafield, east of Inverness, to Balloch and then on from Balloch to the Nairn Bypass.

Completion of the preparatory work, including approval of the Business Case, will enable a firm timetable for delivery to be set as part of the annual budget setting process, with a view to commencing procurement of the main works contract for the Nairn Bypass within this Capital Spending Review period.

The Capital Spending Review allows for the commencement of the construction of the Nairn Bypass in 2029-30, subject to business case approval and confirmation of funding beyond the spending review period. Delivery of advanced works for the Seafield to Balloch section of the scheme are also expected to commence during this capital spending review period.

Despite the current fiscal position and following the A96 Dualling Inverness to Nairn (including Nairn Bypass) scheme, the Scottish Government will continue to progress dualling of the A96 eastwards, including an Elgin Bypass.