Current status: Answered by Fiona Hyslop on 17 March 2026
To ask the Scottish Government what discussions it has had with Transport Scotland regarding options available for a permanent solution for the M8 Woodside viaducts.
The Scottish Government engages regularly with Transport Scotland, which is responsible for taking forward the M8 Woodside Viaducts Permanent Solution project. Work is in progress to develop the Strategic Outline Case for the project, including consideration of a range of alternative approaches that are currently the subject of a public consultation which runs to 25 March. Feedback from that consultation will be considered alongside other factors to determine the preferred approach for the project, which will balance issues such as engineering, environmental, economic, health and safety and social value considerations. Transport Scotland will discuss the emerging findings from this assessment with the Scottish Government when this work is sufficiently advanced.