Question reference: S6W-39676

  • Asked by: Jamie Greene, MSP for West Scotland, Scottish Liberal Democrats
  • Date lodged: 31 July 2025
  • Current status: Answered by Mairi McAllan on 26 August 2025

Question

To ask the Scottish Government what the average cost per unit has been to deliver an affordable home in each year since 2007, and what assessment it has made of how many additional homes could have been delivered if a greater share of investment had taken place during years when construction costs were lower.


Answer

We publish information on Affordable Housing Supply Programme (AHSP) average cost per unit in our annual out-turn reports, available here: Affordable Housing Supply Programme - More homes - gov.scot. The following table show the average cost per unit to deliver an affordable home in each year since 2007.

Financial Year

Average Cost per Home

Average AHSP Scottish Government Funding per Home

2007-2008

£127,131

£76,507

2008-2009

£126,972

£70,814

2009-2010

£120,511

£63,963

2010-2011

£112,003

£57,013

2011-2012

£117,678

£44,411

2012-2013

£95,426

£37,691

2013-2014

£109,445

£45,661

2014-2015

£114,890

£50,559

2015-2016

£115,697

£52,352

2016-2017

£126,250

£61,058

2017-2018

£137,100

£61,032

2018-2019

£143,839

£65,645

2019-2020

£152,646

£71,630

2020-2021

£158,262

£85,553

2021-2022

£168,121

£75,454

2022-2023

£187,341

£90,429

Local authorities have responsibility for setting out the investment priorities supported through the AHSP, ensuring the delivery of the right homes in the right places. In support of these priorities the AHSP has been increased, with the budget for 2025-2026 now £768 million.

Since 2007 we have delivered more than 139,000 affordable homes, with 99,000 of those being for social rent. We continue to work closely with partners to utilise our investment to help maximise the pace of delivery of affordable homes.