Current status: Answered by Mairi McAllan on 11 August 2025
To ask the Scottish Government whether it plans to extend its Cladding Remediation Programme Single Open Call beyond 30 September 2025.
The Single Open Call (SOC) has been incredibly successful in identifying buildings at risk within the Single Building Assessment (SBA) specification, with over 600 buildings, as of 30 June 2025, being identified for review. As confirmed in the Cladding Remediation Programme: Next Phase Plan of Action published 7 August 2025, funding from Stage One of the SOC has doubled to £20 million. The additional £10m funding will ensure that all eligible EOIs received by 31 December 2025 will be able to move forward. We strongly encourage all building owners and their representatives to continue to submit their buildings to the SOC ahead of 31 December 2025.
As well as enhancing funding for Stage One, the Cladding Remediation Programme: Next Phase Plan of Action also confirms the launch of Stage 2 of the Single Open Call. This will allow owners, or their representatives, to seek Scottish Government support for any required mitigation and/or essential cladding remediation works identified through the funded Single Building Assessment at Stage One.