To ask the Scottish Government, further to the answer to the urgent question by Kate Forbes on 14 May 2025, whether it will provide an outline of the work of the small review team that will now meet weekly to discuss the completion of the MV Glen Rosa.


Answer

The purpose of the Glen Rosa review group is to interrogate the revised delivery plan to ensure it is realistic, efficient and focused on value for money.