Current status: Answered by Kate Forbes on 29 May 2025
To ask the Scottish Government which budget the additional funds, which Ferguson Marine has reportedly requested to complete the MV Glen Rosa by Q2 2026, will be drawn from.
The Scottish Government is working with Ferguson Marine and CMAL to understand fully the basis of the revised delivery plan for MV Glen Rosa. All requests for an additional budget for capital projects require detailed scrutiny processes before they can be approved and decisions taken on sources of funding within the overall Scottish Budget.