Skip to main content
Loading…

Chamber and committees

Question reference: S6W-37217

  • Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
  • Date lodged: 28 April 2025
  • Current status: Answered by Gillian Martin on 8 May 2025

Question

To ask the Scottish Government whether the budget for private contractors providing services for Scottish Water was overspent in 2024-25, and, if so, by how much, and what the reasons were for the overspend.


Answer

As this is an operational matter for Scottish Water, and the Scottish Government does not hold the information, I have asked them to respond. Their reply is as follows:

Scottish Water (Regulated) Contractor P&L expenditure for 2024-25 was £31.7m against a Budget of £30.7m. The actual costs include £4.0m unbudgeted proactive leakage recovery costs so therefore the underlying variance is favourable.