Skip to main content
Loading…

Chamber and committees

Question reference: S6W-17458

  • Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
  • Date lodged: 25 April 2023
  • Current status: Answered by Kevin Stewart on 9 May 2023

Question

To ask the Scottish Government what discussions it has had with Strathclyde Partnership for Transport (SPT) regarding financial support to permanently extend the daily operating hours of the Glasgow Subway once the full modernisation programme has been completed, including the installation of Platform Screen Doors (PSDs) in all Subway stations to enable unattended train operation (UTO).


Answer

Strathclyde Partnership for Transport (SPT) is the owner and operator of Glasgow Subway and they are responsible for decisions and funding for subway operations.

The Scottish Government is providing up to £246 million to SPT, towards the estimated total project cost of £287.5 million for the Subway modernisation programme, which includes: a smartcard ticketing system; new rolling stock and signalling; refurbished stations with improved accessibility.

Operation times are a decision for SPT and this is not a matter they have raised with the Scottish Government.