Question reference: S6W-15937
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
- Date lodged: 20 March 2023
-
Current status: Answered by Kevin Stewart on 5 April 2023
Question
To ask the Scottish Government, in light of its announcement in June 2022 that £30 million would be spent “this financial year” to “accelerate the shift to zero emission transport”, how much of this funding it has spent to date, broken down by what it has been spent on; which geographical areas it has been spent in, and whether it has been allocated to (a) the corporate sector, (b) charitable organisations, (c) individuals and (d) others.
Answer
Of the £30 million support that was announced in June 2022, £28 million was allocated to the Low Carbon Transport Loan and the remaining £2 million was allocated to the Plugged-In Communities Schemes. Both have been fully allocated and are pending final claims being received.
Table 1 below gives a breakdown of loans paid under of the Low Carbon Transport loan by local authority area and type of recipient, reflecting payments up to 28 February 2023.
Table 1: Low Carbon Transport Loan – paid loans in financial year 22-23 to 28 February 2023 | |||||
Local Authority Area | New Business Loan | Switched on Taxis Loan | Used Domestic Loan | Used Business Loan | Grand Total (to 28-02-23) |
Argyll and Bute | £0.00 | £0.00 | £193,983.50 | £46,800.00 | £240,783.50 |
Highland | £130,000.00 | £0.00 | £325,320.98 | £39,194.00 | £494,514.98 |
Na h-Eileanan Siar | £29,495.00 | £0.00 | £38,744.00 | £0.00 | £68,239.00 |
Orkney Islands | £0.00 | £0.00 | £59,093.00 | £27,600.00 | £86,693.00 |
Aberdeen City | £58,499.00 | £150,000.00 | £521,317.56 | £109,394.00 | £839,210.56 |
Aberdeenshire | £30,000.00 | £30,000.00 | £794,529.23 | £121,936.50 | £976,465.73 |
Angus | £30,000.00 | £0.00 | £250,730.00 | £59,398.00 | £340,128.00 |
Dundee City | £53,684.56 | £28,195.00 | £513,198.20 | £28,295.00 | £623,372.76 |
Moray | £0.00 | £0.00 | £147,881.00 | £0.00 | £147,881.00 |
Perth and Kinross | £34,999.00 | £0.00 | £641,044.60 | £92,617.00 | £768,660.60 |
City of Edinburgh | £90,979.00 | £831,821.44 | £1,697,763.01 | £123,612.00 | £2,744,175.45 |
East Lothian | £0.00 | £34,093.00 | £587,197.00 | £0.00 | £621,290.00 |
Fife | £35,000.00 | £63,805.00 | £800,616.00 | £0.00 | £899,421.00 |
Midlothian | £0.00 | £121,898.20 | £432,242.00 | £0.00 | £554,140.20 |
Scottish Borders | £0.00 | £0.00 | £377,066.00 | £23,500.00 | £400,566.00 |
West Lothian | £70,000.00 | £128,473.00 | £475,531.81 | £0.00 | £674,004.81 |
Dumfries and Galloway | £0.00 | £0.00 | £285,852.00 | £11,499.00 | £297,351.00 |
East Ayrshire | £0.00 | £0.00 | £134,602.21 | £111,834.00 | £246,436.21 |
North Ayrshire | £0.00 | £0.00 | £144,256.06 | £28,437.60 | £172,693.66 |
South Ayrshire | £120,000.00 | £93,658.00 | £204,350.00 | £25,200.00 | £443,208.00 |
Clackmannanshire | £0.00 | £0.00 | £154,468.00 | £0.00 | £154,468.00 |
East Dunbartonshire | £60,000.00 | £252,771.40 | £324,659.03 | £25,198.80 | £662,629.23 |
East Renfrewshire | £0.00 | £185,751.80 | £436,581.00 | £89,498.00 | £711,830.80 |
Falkirk | £51,165.48 | £0.00 | £353,921.00 | £27,500.00 | £432,586.48 |
Glasgow City | £130,000.00 | £586,127.60 | £1,286,187.01 | £168,160.00 | £2,170,474.61 |
Inverclyde | £31,093.50 | £0.00 | £222,936.93 | £0.00 | £254,030.43 |
North Lanarkshire | £0.00 | £154,718.00 | £575,597.99 | £0.00 | £730,315.99 |
Renfrewshire | £0.00 | £148,558.00 | £273,222.00 | £67,507.30 | £489,287.30 |
South Lanarkshire | £152,629.00 | £152,001.10 | £815,437.47 | £100,186.60 | £1,220,254.17 |
Stirling | £97,000.00 | £0.00 | £790,167.00 | £22,700.00 | £909,867.00 |
West Dunbartonshire | £0.00 | £0.00 | £119,368.00 | £23,149.00 | £142,517.00 |
Grand Total | £1,204,544.54 | £2,961,871.54 | £13,977,863.59 | £1,373,216.80 | £19,517,496.47 |
Tables 2 and 3 below give a breakdown of payments under the Plugged-in Communities schemes, reflecting payments up to 28 February 2023. Table 2 reflects payments to Community Transport Organisations, and Table 3 reflects payments to car clubs.
Table 2: Plugged-in Communities, Grants to Community Transport Organisations, payments in financial year 22-23 to 28 February 2023 | ||
Local Authority Area | Amount Paid | Community Transport Organisation. |
Highland | £83,603.70 | Wheels in Nairnshire |
Orkney | £80,856.00 | Island of Hoy Development Trust |
Argyll and Bute | £66,638.00 | Ross of Mull and Iona Community Trust |
Highland | £67,371.40 | Transport for Tongue |
Aberdeen | £76,535.00 | Clan Cancer Support |
Dumfries and Galloway | £46,000.00 | Galloway Community Transport |
Aberdeen | £76,535.00 | Camphill School Aberdeen |
West Lothian | £41,979.80 | The Larder (West Lothian) |
Dumfries and Galloway | £71,040.00 | Annandale Community Transport |
Highland | £8,400.00 | Connect Assynt |
Total | £618,958.90 |
Table 3: Plugged-in Communities, Grants to Car Clubs, payments in financial year 22-23 to 28 February 2023 | ||
Local Authority Area | Amount Paid | Car Club |
Aberdeen | £13,801.68 | Grampian Housing Association |
Renfrewshire | £3,375.00 | Linstone Housing Association |
Glasgow | £9,201.12 | Queens Cross Housing Association |
Glasgow | £15,335.14 | Glasgow Housing Association |
Aberdeen | £10,351.25 | Osprey Housing Association |
Fife | £19,584.00 | Ore Valley Housing Association |
City of Edinburgh | £39,168.00 | Blackwood Group |
Total | £110,816.19 |