Question
To ask the Scottish Government what evidence-based appraisals of fixed links as solutions to strategic problems were carried out in preparation of Strategic Transport Projects Review 2.
Answer
The outcomes of the transport appraisal that supported second Strategic Transport Projects Review(STPR2), was published on the 8 December 2022 on the Transport Scotland website.
The appraisal was conducted in several phases which involved ongoing stakeholder engagement. The eleven regional and national Case for Change Reports were published in February 2021 and further details on these can be found here: STPR2 strategic approach | Transport Scotland .
Appendix D and E of the National Case for Change Report Initial appraisal: Case for Change - National - STPR2 | Transport Scotland , respectively detail those options sifted “in” and “out” for further consideration at next appraisal stage.
The outcomes of this final detailed appraisal, including details of the approach followed to appraise options, are contained in the published Final technical report - December 2022 - STPR2 | Transport Scotland .
Specific details on the results of the appraisal related to Recommendation 41 – Potential Fixed Links across the Sounds of Barra, Harris and between Mull and the Mainland can be found here: recommendation-41-potential-sound-of-harris-sound-of-barra-fixed-link-and-fixed-link-between-mull-and-scottish-mainland.pdf (transport.gov.scot)