Question

To ask the Scottish Government whether it is the case that only two of its buildings have a heat pump installed; what action it will take to increase the number of its buildings that have a heat pump installed, and within what timescale will any such action be undertaken.


Answer

Currently 1 building on the core Scottish Government estate has a heat pump installed (Tweedbank)

Feasibility studied will be carried out in the first quarter of 2023/24 financial year to look at a range of renewable technologies for the estate, including air source heat pumps.

Timescale for installing air source heat pumps to suitable buildings:-

  • 2023-24 – (1st quarter) - Feasibility studies will be carried out with business cases and funding applications submitted for suitable projects.
  • 2023-24 – (2nd quarter) - Apply, design and install power cable upgrades if required or – if the incoming power needs to be increased from the supplier.
  • 2023-24 – (3rd/4th quarter quarter) - Design, tender, appoint a contractor, planning permissions
  • 2024-25 – Installation of ASHP, radiators, pipework.