Question reference: S6W-14231

  • Asked by: Collette Stevenson, MSP for East Kilbride, Scottish National Party
  • Date lodged: 23 January 2023
  • Current status: Answered by John Swinney on 1 February 2023

Question

To ask the Scottish Government what estimate it has made of the (a) total spend to date on, (b) costs in the financial year 2021-22 for and (c) expected costs in the financial year (i) 2022-23 and (ii) 2023-24 for, the repayment of Private Finance Initiative/Public Private Partnership (PFI/PPP) debts, including the (A) overall cost to (1) the NHS, (2) local government, (3) justice portfolio bodies, (4) net zero, energy and transport portfolio bodies and (5) any other public sector organisations in Scotland and (B) cost to each individual (aa) NHS board, (bb) local authority and (cc) other regional authority.


Answer

Information relating to Private Finance Initiative (PFI) and Non-Profit Distributing (NPD) contracts and their associated unitary charge payments, is available from the Scottish Government website by way of the following link www.gov.scot