Question

To ask the Scottish Government what the £6 million of reduced Buildings Standards expenditure identified on page 23 of the Emergency Budget Review was originally assigned to.


Answer

The budget allocated to the Cladding Remediation programme is £400 million in total, this includes the £6 million identified in the Emergency Budget Review. The focus of funding in this financial year has been on expanding our pilot towards 100 surveys, surveys cost less than remediation but are a key commitment and an essential step before remediation work can start. There has been no impact on projects or on the overall budget.