Question reference: S6W-04873

  • Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
  • Date lodged: 6 December 2021
  • Current status: Answered by Graeme Dey on 20 December 2021

Question

To ask the Scottish Government what the proposed timescale is for the commencement of works on the site of the former car park to the east of Glasgow Queen Street Station to build a new North Hanover Street entrance and podium building for operational and passenger facilities, including retail, and what the expected duration of the project will be.


Answer

In the summer of 2020, the Scottish Government undertook a Capital Spending Review of its capital budgets against the backdrop of Covid-19, which necessitated a review of rail enhancements priorities.

Following the 2020 review, amid significant financial pressures on the available rail enhancements capital budget, the North Hanover Street development was deferred. Against a backdrop of rising costs and pressures on the rail enhancements budget, Network Rail was instructed to return to Transport Scotland with a proposal to progress the development, with options for alternative funding.

Transport Scotland await a revised proposal from Network Rail. Officials continue to remain engaged in regular meetings with key stakeholders such as Glasgow City Council, Network Rail and Scottish Futures Trust aimed at keeping each other updated in respect of developments in and around the Queen Street station area.