Skip to main content
Loading…

Chamber and committees

Question reference: S4W-21756

  • Asked by: Alison Johnstone, MSP for Lothian, Scottish Green Party
  • Date lodged: 13 June 2014
  • Current status: Answered by Fergus Ewing on 25 June 2014

Question

To ask the Scottish Government when the next periodic safety review is due for (a) Hunterston B and (b) Torness nuclear power station.


Answer

<>The next periodic safety review (PSR) for Hunterston B is due to be submitted by the site licensee in January 2016, and the Office for Nuclear Regulation (ONR) will make a decision on this in January 2017.

For Torness, the PSR is due to be submitted by the site licensee in January 2019, and the ONR decision date is January 2020.