Question

To ask the Scottish Executive how much of the Historic Buildings Repair Grants Scheme in 2002-03 (a) has been committed in (i) grant awards in total and (ii) indicative offers of grant and (b) remains uncommitted.


Answer

I have asked Graeme Munro, Chief Executive of Historic Scotland to respond. His response is as follows:The position as at 31 October 2002 was as follows:

 £ million
Budget11.1
Firm offers7.1
Indicative authorisations2.3
Pre-offer stage - uncommitted funds0.9
Recurring expenditure2.4
Total12.7