Question reference: S5W-09028

  • Asked by: Stewart Stevenson, MSP for Banffshire and Buchan Coast, Scottish National Party
  • Date lodged: 26 April 2017
  • Current status: Answered by Humza Yousaf on 10 May 2017

Question

To ask the Scottish Government how much has been spent on trunk roads in the (a) Aberdeen City, (b) Aberdeenshire, (c) Angus, (d) Dumfries and Galloway, (e) Dundee, (f) Fife, (g) Highland, (h) Moray, (i) Perth and Kinross, (j) Scottish Borders and (k) Stirling council area in each year since 1999, broken down by type of expenditure.


Answer

We are committed to the largest road investment programme that Scotland has ever seen. By the end of this financial year (2016-17), we will have spent over £8 billion on our Motorways and Trunk Road Network since 2007, to ensure the strategic road network is safe, available for use, efficient, well maintained and allows effective movement of people, goods and services around and to and from Scotland.

On-Going Schemes

Since 2007, the Scottish Government has invested in a number of major roads projects, including:

Project

Investment

Forth Replacement Crossing

£1.325 to £1.35 billion

Aberdeen Western Peripheral Route/Balmedie-Tipperty

£745 million

M8 M73 M74 Motorway Improvements Project

£500 million

A9 Dualling

£3 billion

A96 Dualling

£3 billion

A737 Dalry Bypass

£34 – 38 million

In addition, the Scottish Government continues to progress the design and development of a number of schemes including the A90/A937 Laurencekirk Junction Improvement and the A90/A96 Haudagain Junction Improvement.

A breakdown by road and local authority area is not possible for incomplete schemes as some of the investments are of a national nature (e.g. Forth Replacement Crossing) and others span a number of local authority areas. However, analysis of spend by year, since 2007-08 can be seen in the following table.

Year

Annual Motorways And Trunk Road Budget

2007-08

£895.1m

2008-09

£929.6m

2009-10

£1,081.6m

2010-11

£1,167.5m

2011-12

£553.9m

2012-13

£651.7m

2013-14

£711.8m

2014-15

£677.7m

2015-16

£734.4m

Sub Total 2007-08 to 2015-16

£7,403.3m

2016-09-2717 Draft Budget Note 1

£820.3m

TOTAL

£8,223.6m

Figures from 2011-12 onwards exclude Cost of Capital which was abolished. Cost of Capital Figures from 2007-08 to 2010-11 are £517.8m, £546.5m, £595.5m and £649.1m respectively.

[1] Figures taken from respective January Scottish Budget Bills.

Completed Schemes

Scheme

Contract Value

Main Local Authority

A90 Kinfauns & Glendoick Interchanges

13.87m

Dumfries and Galloway Council

A9 Ballinluig

 

12.5m

Perth and Kinross Council

A75 Overtaking Opportunities (Including A75 Newton Stewart, A75 Planting End to Drumflower, A75 Barfil to Bettyknowes)

 

9.2m

The Highland Council

A9 Helmsdale

 

5.5m

Midlothian Council

A68 Dalkeith Bypass

 

30m

Clackmannanshire, Falkirk and Fife Councils

M8 Harthill Footbridge

5.1m

South Ayrshire Council

A876 Clackmannanshire Bridge

 

101.5m

Dumfries and Galloway Council

A77 Haggstone and Glen App

 

18.7m

The Highland Council

A76 Glenairlie

 

4.9m

Dumfries and Galloway Council

A830 Arisaig to Loch nan Uamh

 

22.8m

Perth and Kinross Council

A7 Auchenrivock

 

7.7m

Dumfries and Galloway Council

A9 Bankfoot

 

3.2m

South Ayrshire Council

A75 Cairntop to Barlae

 

6.4m

North Lanarkshire, Falkirk, Glasgow City

A77 Park End to Bennane

 

5.5m

Glasgow City, East Renfrewshire

M74 Completion

 

445m

The Highland Council

A9 Crubenmore

10.39m

Moray Council

M80 Stepps to Haggs

 

320m

 

Dumfries and Galloway Council

A96 Fochabers to Mosstodloch

 

31.5m

South Ayrshire Council

A75 Dunragit Bypass

 

17.1m

Argyll and Bute Council

A77 Symington to Bogend Toll

 

10.6m

Stirling Council, Argyll and Bute Council

A75 Hardgrove to Kinmount

 

8.97m

Dumfries and Galloway Council

A82 Crianlarich Bypass

5m

Aberdeenshire

A82 Pulpit Rock

9.2m

 

A96 Inveramsay Bridge

10.2m

 

Maintenance Investment

The following table for maintenance investment provides spend figures by route and by year for Trunk Road Operating Company expenditure, including structural maintenance, minor improvements, routine maintenance, strategic road safety, bridges and structures and winter service.In addition the table includes expenditure in respect of PFI payments for the M74, M77, and M80 Design Build Finance and Operate (DBFO) schemes, Scottish Safety Camera Parnership, Forth Estuary Transport Authority (up to June 2015), Tay Road Bridge Joint Board and Traffic Scotland.

 

Maintenance Spend (£)

Route

2007-08

2008-09

2009-10

2010-11

2011-12

2012-13

2013-14

2014-15

2015-16

2016-17 (spend up to October 2016)

A1

3,991,119

1,841,392

3,906,589

3,699,577

2,893,348

2,589,814

2,836,167

2,790,934

3,286,268

1,128,471

A6091

111,963

120,845

316,990

385,785

378,411

175,047

255,621

148,953

122,392

80,105

A68

1,194,103

3,246,448

2,698,924

3,245,730

2,419,030

2,224,427

2,708,490

3,089,996

2,685,355

2,230,465

A7

1,348,817

2,745,091

3,565,093

2,203,701

2,321,705

2,577,865

3,049,681

2,777,387

2,458,251

2,290,005

A701

679,284

922,931

726,830

1,121,126

854,450

1,103,368

1,258,741

1,596,879

2,411,032

636,491

A702

1,340,807

2,186,757

2,393,352

2,951,047

2,081,130

2,385,520

2,821,872

1,444,215

1,618,802

1,797,366

A720

1,818,719

756,953

1,408,309

1,745,292

1,201,259

1,086,351

1,371,748

1,009,518

1,595,546

1,464,319

A725

1,801,663

1,433,578

1,540,450

1,328,252

1,339,200

1,443,047

1,237,845

738,297

1,017,379

517,508

A726

(370,197)

85,663

124,580

122,555

63,191

189,683

281,836

78,160

79,722

40,845

A737

3,145,033

3,247,086

1,349,300

1,396,651

1,648,479

1,658,525

966,867

834,588

1,440,045

933,626

A738

102,790

61,098

66,312

106,801

70,486

87,752

35,202

42,812

193,009

52,165

A75

4,044,719

5,181,289

6,685,268

5,261,670

5,271,982

8,217,953

7,471,482

7,142,158

6,817,839

6,087,268

A751

62,080

79,585

306,459

64,725

73,450

383,130

106,095

1,040,264

30,805

31,095

A76

3,641,793

2,787,184

4,116,188

6,952,699

3,386,832

4,446,513

2,379,291

2,928,613

2,831,220

2,735,243

A77

5,175,014

4,860,299

4,678,778

4,832,029

4,017,769

5,555,230

4,595,502

4,712,140

4,326,055

3,167,117

A78

2,114,105

2,742,212

3,588,536

3,637,857

2,636,842

3,889,111

2,735,848

2,906,333

3,096,194

2,512,447

A8

1,350,755

1,091,815

1,690,031

986,424

1,140,910

1,012,370

488,831

679,417

415,617

644,422

A80

2,008,936

262,206

11,756

0

3,324

4,755

84

0

0

0

A82

9,296,757

10,975,038

10,511,800

10,630,253

6,991,720

9,365,621

6,923,597

8,116,033

9,312,907

5,239,176

A823

2,002,684

3,648

1,855,598

5,315

0

298

390

130

2,994

15,832

A828

1,427,766

1,005,509

1,169,019

868,874

1,040,861

1,483,712

927,043

819,380

731,776

481,805

A83

7,097,160

5,322,577

6,113,849

5,108,115

2,128,685

7,166,174

6,270,841

8,835,218

5,039,324

2,340,718

A830

1,346,735

1,566,839

1,416,460

2,236,853

1,517,302

1,290,367

880,227

3,249,297

4,057,218

3,020,608

A835

2,929,724

1,194,207

1,868,439

1,449,376

1,672,107

1,640,618

1,442,241

1,320,359

1,033,984

756,282

A84

1,287,343

1,145,814

2,109,804

1,103,977

1,128,142

1,075,711

1,318,825

1,335,399

1,089,892

742,572

A85

4,396,377

2,705,506

4,724,410

2,895,019

4,635,874

4,859,046

3,654,239

3,666,410

4,477,419

2,330,288

A86

1,142,080

1,224,461

1,244,793

1,009,788

1,730,579

1,466,607

652,314

1,925,454

911,084

703,951

A87

5,711,475

4,445,783

7,549,904

5,483,310

3,696,512

2,680,628

2,493,465

2,801,907

3,827,966

2,350,086

A876

231,429

187,508

129,803

167,915

233,092

133,019

161,615

210,419

229,942

192,381

A887

229,056

331,016

306,999

426,515

383,349

526,201

209,473

256,293

278,055

454,555

A889

585,323

224,454

196,384

225,853

216,766

204,614

261,151

325,919

188,822

286,997

A893

0

0

0

0

0

0

2,510

2,311

2,222

1,517

A898

3,482,235

3,320,263

5,220,163

2,296,688

2,550,402

4,519,096

7,665,036

5,702,470

2,747,956

3,658,105

A9

21,822,422

11,376,915

21,809,173

19,787,634

10,896,569

19,411,813

23,496,740

21,359,900

13,776,006

10,680,537

A90

10,568,555

12,848,608

6,784,257

10,608,122

9,097,220

9,176,757

10,663,545

8,593,692

21,218,245

8,042,323

A92

3,163,533

3,156,805

5,939,518

2,740,500

2,811,267

2,129,936

4,191,232

2,817,110

3,166,597

2,812,288

A95

1,997,567

1,937,702

2,508,776

2,917,667

3,127,941

1,997,365

3,071,792

2,558,230

4,735,944

615,705

A96

6,299,843

6,777,244

6,595,227

6,828,041

5,967,893

4,677,149

5,691,119

4,877,528

3,266,481

2,854,140

A972

53,034

18,159

20,591

48,560

44,662

100,709

130,676

72,421

253,130

18,797

A977

63,539

68,970

76,346

191,791

111,009

100,629

119,085

99,450

394,172

36,207

A985

2,193,924

1,606,592

754,834

572,892

839,287

628,204

783,159

1,533,006

879,071

922,977

A99

649,300

447,336

537,896

664,864

473,804

881,274

321,336

363,349

426,855

150,619

M73

1,508,752

2,012,914

406,116

289,620

316,143

304,590

128,816

14,873

0

0

M74

12,813,517

8,543,506

4,202,742

3,841,147

3,782,891

3,519,374

3,396,650

2,373,496

3,117,129

2,023,581

M77

4,741,872

996,477

652,282

841,436

715,450

939,969

854,582

305,048

837,746

227,561

M8

13,792,040

17,732,399

17,263,989

12,938,570

8,587,775

10,423,339

8,088,710

12,656,019

11,647,244

4,698,984

M80

6,874,041

483,003

1,207,418

973,856

1,065,525

1,933,283

1,613,103

553,613

1,249,992

745,066

M823

28,214

48,558

52,125

58,698

84,681

65,157

82,716

130,898

474,437

539,264

M876

159,355

913,737

1,046,225

1,627,226

837,609

660,438

889,604

1,157,748

959,405

209,017

M898

47,830

214,457

301,449

198,173

83,216

58,872

51,698

66,001

87,950

26,134

M9

5,833,861

6,563,358

6,301,940

5,200,643

3,698,219

5,821,693

6,252,114

4,084,243

4,493,735

4,931,633

M90

4,559,983

2,796,874

1,885,092

4,566,362

2,997,032

4,834,884

4,371,780

3,560,754

6,155,152

6,843,714

Total Spend per Route (£m)1

171.9

145.8

161.9

148.8

115.3

143.1

141.7

139.7

145.6

95.4

PFI payments2

41.9

41.6

40.6

48

62

74.5

76.8

84.7

91

 

Other payments3

31.8

29.6

31.3

46.6

54.5

26.0

41.0

41.1

38.6

 

Total Maintenance spend (£M)

245.6

217

233.8

243.4

231.8

243.6

259.5

265.5

275.2

 

1. Figures for spend per route include structural maintenance spend, minor improvements, route maintenance, strategic road safety, bridges and structures and winter service

2. 3. PFI payments and Other payments (e.g. safety camera partnership, Forth Estuary Transport Authority/Tay Road Bridge Joint Board and Traffic Scotland service) are not route specific but are included for completeness